Power Distribution & Reforms

Update: Discom Finances According to the 14th Integrated Rating and Ranking report (Power Finance Corporation, released January 2026, FY25 data), distribution utilities posted an aggregate…

Chapters in this report (6)

Update: Discom Finances

  • According to the 14th Integrated Rating and Ranking report (Power Finance Corporation, released January 2026, FY25 data), distribution utilities posted an aggregate profit after tax of Rs 2,701 crore in FY25, against a loss of Rs 27,022 crore in FY24. This was the first aggregate profit on an accrual basis.
  • The same report puts aggregate technical and commercial (AT&C) losses at 15.04% in FY25, down from 15.97% in FY24, with billing efficiency of 87.59% and collection efficiency of 97.0%.
  • Of 72 utilities, 65 participated; 31 earned an A+ or A grade and 11 earned a C or C-.
  • Analysts note that accumulated discom losses remain large (about Rs 6.47 trillion at the end of FY25, according to one commentary) and that part of the improvement reflects enforcement and accounting changes rather than tariff increases.
  • The Ministry of Power has extended the Revamped Distribution Sector Scheme (RDSS) smart-meter target of 25 crore meters to March 2028. ICRA has pointed to execution delays in the rollout.

Power Distribution Industry

Distribution is the last link in the supply chain and is largely owned by state discoms and electricity boards. Its performance depends on reducing AT&C losses, setting cost-reflective tariffs, timely payment of state subsidies and reliable supply. Distribution has been the weakest part of the value chain since the Electricity Act, 2003.

Earlier data (FY22): the average cost of supply was Rs 6.29 per kWh against average revenue of Rs 4.98 per kWh excluding subsidy.

Challenges for Discoms

  • AT&C losses: Feeder and distribution-transformer metering, consumer indexing, GIS mapping and smart metering are used to reduce them.
  • Tariff and subsidy gaps: Delayed tariff filings, late state subsidy payments and growing regulatory assets reduce cost recovery.
  • Legacy power purchase agreements (PPAs): Thermal plants contracted on long-term two-part tariffs earn capacity charges (roughly 45-50% of tariff) even when not scheduled, while renewables have must-run status.
  • Working capital: Payment delays to generators have historically strained the sector.

Installed Capacity by Ownership (31 May 2024, CEA)

SectorMWShare
Central1,04,45323.5%
State1,07,67124.2%
Private2,32,63352.3%
Total4,44,757

Frequently asked questions

What is covered in Power Distribution & Reforms?

Distribution is the last link in the supply chain and is largely owned by state discoms and electricity boards. Its performance depends on reducing AT&C losses, setting cost-reflective tariffs, timely payment of state subsidies and reliable supply.

What does this chapter say about Update: Discom Finances?

The same report puts aggregate technical and commercial (AT&C) losses at 15.04% in FY25, down from 15.97% in FY24, with billing efficiency of 87.59% and collection efficiency of 97.0%; Of 72 utilities, 65 participated; 31 earned an A+ or A grade and 11 earned a C or C-.

What does this chapter say about Power Distribution Industry?

Distribution is the last link in the supply chain and is largely owned by state discoms and electricity boards. Its performance depends on reducing AT&C losses, setting cost-reflective tariffs, timely payment of state subsidies and reliable supply.

What does this chapter say about Challenges for Discoms?

AT&C losses: Feeder and distribution-transformer metering, consumer indexing, GIS mapping and smart metering are used to reduce them; Tariff and subsidy gaps: Delayed tariff filings, late state subsidy payments and growing regulatory assets reduce cost recovery.

Back to the full Indian Power Generation & Distribution Sector Report →

Disclaimer: Investment in securities market are subject to market risks. Read all the related documents carefully before investing. Registration granted by SEBI, membership of a SEBI recognized supervisory body (if any) and certification from NISM in no way guarantee performance of the intermediary or provide any assurance of returns to investors.

The content in these posts/articles is for informational and educational purposes only and should not be construed as professional financial advice and nor to be construed as an offer to buy/sell or the solicitation of an offer to buy/sell any security or financial products. Users must make their own investment decisions based on their specific investment objective and financial position and using such independent advisors as they believe necessary.

Wryght Research & Capital Pvt (Brand name: Wright Research) is a SEBI Registered Portfolio Manager Reg No: INP000007979 (Validity: Apr 03, 2023 – Perpetual) and a SEBI Registered Research Analyst No: INH000017295 (Validity: Jul 03, 2024 – Perpetual), with its registered office at 103, Shagun Vatika Prag Narayan Road, Lucknow, UP, 226001 India and CIN: U67100UP2019PTC123244. Past performance may or may not be sustained in future. Performance provided there in is not verified by SEBI. Investment in securities is subject to market and other risks, and there is no assurance or guarantee that the objectives of any of the strategies of the Portfolio Management Services will be achieved. Registration granted by SEBI, enlistment as RA with Exchange and certification from National Institute of Securities Markets (NISM) in no way guarantee performance of the intermediary or provide any assurance of returns to investors. Please read the Disclosure document carefully before investing. Securities quoted are for illustration only and are not recommendatory. Charts shown are for illustration only. For more information and disclosures, visit our disclosures page here.